your location:powerful sam>sam news
powerful sam
hot news
news flash | the lng project of jiangsu honghai energy co., ltd. lighted up for the first time



on december 17, 2020, the lng project of jiangsu honghai energy co., ltd. was lit for the first time, which meant and the low-voltage system of the project was successfully delivered.
chen qingbing, the general manager of honghai energy, introduced that in order to ensure the power transmission of the low-voltage system under the special conditions of not having the power in place officially, a temporary scheme for power transmission was formulated. the project management department of honghai compiled the transmission scheme with the general contractor, the construction organization and the supervision to define the scope of transmission, the receiving time and safety control elements. at the same time, the low pressure system comprehensive screening was carried out to rectify the discovered problem so as to ensure the safety of low pressure system. the success of the power transmission was an important node in the process of project construction because it provided the precondition for inspecting construction and equipment quality, which meant the project has entered into the stage of equipment commissioning and intermediate handover and laid a solid foundation for the formal operation.
the honghai energy lng project involves two lng storage tanks of 80,000 cubic meters with supporting technologies, public utilities and auxiliary facilities, and has a transshipment capacity of 2 million tons per year which is equivalent to 2.8 billion cubic meters of gaseous natural gas. it will be completed by the end of 2020 and put into trial production in july 2021.


source:zhongxing tianheng energy technology