news flash | jiangsu honghai energy co., ltd. independently implemented the drying replacement project of lng storage tanks

2021-03-22 04:52:06
clicks:26 次

on march 3, 2021, the lng storage and distribution station project invested and constructed by jiangsu honghai energy co., ltd., controlled by zhongxing tianheng energy technology (beijing) co., ltd. (stock code: 600856), officially started the drying replacement project. the tank is the first largest lng storage one with metallic wall covered both sides in china. the outer diameter of the tank is 60m, the inner one is 58m and the height is 50m. the material of both inner and outer of the tank are made of domestic low-temperature ni9 steel.



compressor start-up


the purpose of the drying replacement was to reduce the inner dew point and oxygen content of the storage tank, so as to prevent the risks caused by the mixed air and the water freezing at the low temperature when the lng first entered into the tank. the air source for tank drying replacement was provided by the leased skid-mounted oil-free screw air compressor, micro-thermal regenerative dryer and psa nitrogen system. the continuous displacement mode of charging and pressure relief were adopted for the inner tank and annular space of the tank. when the dew point reached the control requirements, nitrogen was filled in the inner tank and annular space at the same time, while the tank pressure was keeping at 3kpa.


the drying replacement of lng storage tanks was carried out by honghai energy group after multiple rounds of researches and comparisons. the independent implementation was the first of its kind in the lng industry, which fully reflected the technological innovation ability and the spirit of taking responsibility of the company. in order to achieve the security requirements and the stability to ensure the quality of drying replacement, the leaders of the company attached great importance to the project and set up the special management team for tank drying replacement led by the general manager. by communicating with the china huanqiu contracting & engineering co., ltd. about the technical requirements, the company optimized the scheme, organized and trained the workers, analyzed the special risk jsa, and wrote 《the drying replacement project of lng storage tank》,《the safety analysis on the project of lng storage tank drying replacement》to instruct the implementing condition, the supplies needed, the manpower demand, the operating procedure, the technique required, the controls parameter, the potential risks and the safety control measures. 


special skills training


at the same time, the company invited professional engineers to train operators on the using of instruments and materials, monitoring and operating key points as well as the safety precautions. besides, the company asked the equipment manufacturer to give instructions on the air compressor and dryer in terms of operation considerations and fault handling methods to effectively improve the pragmatic skills and safety consciousness of the operators.


through the independent implementation of the drying replacement project, the implementation cost of the system has been greatly reduced, the actual operation capacity and technical level of production have been improved, which meant a solid foundation has been laid for the trial production of the lng storage and distribution station in july 2021.


source:zhongxing tianheng energy technology